The CCC has received the following from SPR following it's trial run last week:
Following the trial run, the team have identified some additional works that are required in the areas below. These will be completed between now and the end of the month and will require traffic management for a few days at each area (specific dates are to be confirmed):
A75 junction with A751 (https://what3words.com/alley.missions.chop)
A75 junction with Barnkirk Rd (https://w3w.co/generated.deduct.sensible)
A714 junction with Barnkirk Rd / Linloskin Bridge Junction (https://w3w.co/typed.during.wipe)
In addition, similar to before, there will be some vegetation cutting taking place along the route, where traffic management will maintain traffic flow. This will only be required for a few hours at each location.